SAP C-TS412-2021 exam consists of 80 multiple-choice questions that must be answered within 180 minutes. C_TS412_2021 exam is available in English and is delivered online. Candidates who pass the exam will earn the SAP Certified Application Associate - SAP S/4HANA Project Systems certification, demonstrating their proficiency in SAP S/4HANA Project Systems implementation. SAP Certified Application Associate - SAP S/4HANA Project Systems certification is recognized globally and can help professionals advance their careers in project management.

 

NEW QUESTION # 39
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?

  • A. Set up the requirement date manually as February 5.
  • B. Set up the requirement date aligned with the activity start date and an offset of 5 days
  • C. Set up the requirement date aligned with the activity start date and a negative offset of 5 days
  • D. Set up the requirement date aligned with the activity finish date and an offset of 15 days.

Answer: C


NEW QUESTION # 40
What is the reason for assigning billing plans in customer projects?

  • A. Billing plans are copied automatically to the sales order item.
  • B. Billing plans are prerequisites for quotation creation
  • C. Billing plans are used for revenue planning
  • D. Billing plans enable the billing process to be carried out

Answer: C


NEW QUESTION # 41
Project structure
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.

  • A. Project version.
  • B. Project definition
  • C. Standard network
  • D. Standard Project definition
  • E. Project milestone

Answer: A,C,D


NEW QUESTION # 42
Cost & Budget
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation., and have entered the quotation ...
What is the typical sequence for the following business transactions and document.

  • A. Benefic check - Acceptance of performed service- vendor selection - purchase order handing- purchase order monitoring-Good receipt - invoce ..
  • B. Vendor selection - purchase order handing - invoice receipt - purchase order monitoring -Good receipt.
  • C. Vendor selection - purchase order handing- purchase order monitoring- Benefic Check- Acceptance of performed services.
  • D. Vendor selection- Purchase order handing-purchase order monitoring-Good receipt- Invoice receipt.

Answer: D


NEW QUESTION # 43
For which objects can billing plans be created? Note: There are 2 correct answers to this question

  • A. Project definition
  • B. Milestones
  • C. Sales order items
  • D. WBS elements

Answer: B,D


NEW QUESTION # 44
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.

  • A. Operating concern
  • B. Company code
  • C. Controlling area
  • D. Plant
  • E. Sales organization

Answer: B,C,D


NEW QUESTION # 45
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question

  • A. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"
  • B. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"
  • C. You can always maintain the actual start and finish date of a WBS element
  • D. You can only maintain the actual start of a WBS element if the finish date is not maintained

Answer: A,D


NEW QUESTION # 46
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.

  • A. Project definition
  • B. Sales order items
  • C. WBS elements
  • D. Milestones

Answer: B,C


NEW QUESTION # 47
Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.

  • A. Basic dates
  • B. Baseline dates
  • C. Planned dates
  • D. Forecast dates
  • E. Fundamental dates

Answer: C,D

Explanation:
In the SAP Project System, there are different sets of dates that can be scheduled for a network. Some of these sets of dates are:
Planned dates: These are the dates that you enter manually for the network activities and relationships. You can use planned dates to define your own scheduling scenario that may differ from the system-calculated dates.
Forecast dates: These are the dates that are calculated by the system based on the current progress and status of the network activities and relationships. You can use forecast dates to estimate the future dates of the network based on the actual data and remaining work. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html


NEW QUESTION # 48
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?

  • A. The maintenance orders must be assigned to WBS element.
  • B. The maintenance orders must be assigned as sub-networks.
  • C. The maintenance orders must be assigned to the same plant as the network.
  • D. The maintenance order s must be assigned to the same budget profile as the project definition.

Answer: C


NEW QUESTION # 49
You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?

  • A. The manual hierarchical revenue planning will be displayed only if expert mode is activated
  • B. Cost element reports can display costs but not revenues
  • C. The manual hierarchical revenue planning has no reference to cost elements
  • D. Cost element reports display integrated planning only

Answer: C

Explanation:
The reason why the cost element report for planned revenues does not show any revenues at all is that the manual hierarchical revenue planning has no reference to cost elements. Manual hierarchical revenue planning is a type of revenue planning that allows you to plan revenues for WBS elements manually without using sales documents. Manual hierarchical revenue planning does not use cost elements as a basis for planning, but uses revenue elements instead. Revenue elements are a set of data that define the characteristics and properties of a revenue type. Cost element reports can only display data that is based on cost elements, not revenue elements. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 50
What functions are available for period end closing in SAP Project System? Note: There are 3 correct answers to this question

  • A. Settlement
  • B. Results analysis
  • C. Progress analysis
  • D. Confirmations
  • E. Milestone trend analysis

Answer: A,B,C

Explanation:
Settlement, progress analysis, and results analysis are some of the functions available for period end closing in SAP Project System. Settlement is used to allocate the costs and revenues in projects or the results analysis data to one or more receivers, such as cost centers, profitability segments, or assets. Progress analysis is used to determine and compare the planned and actual project progress values, based on the overall planned costs and the work done. Results analysis is used to perform a periodic valuation of the project, based on the costs and revenues expected or incurred in the project. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 51
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question

  • A. In the project version
  • B. In the operative WBS element
  • C. In the project type
  • D. In the project profile
  • E. In the project definition of a standard WBS

Answer: B,D,E


NEW QUESTION # 52
The various work packages in the project are described as individual______________. Choose the correct answer.

  • A. Tasks
  • B. Activities
  • C. Project definitions
  • D. WBS elements

Answer: D


NEW QUESTION # 53
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget?

  • A. Availability control
  • B. Easy Cost Planning
  • C. Results analysis
  • D. Cost forecast

Answer: A


NEW QUESTION # 54
......


SAP C-TS412-2021 certification exam is an online exam that consists of 80 multiple-choice questions. C_TS412_2021 exam is timed and candidates are given 180 minutes to complete the exam. The passing score for the exam is 65% and candidates who pass the exam will be awarded the SAP Certified Application Associate - SAP S/4HANA Project Systems certification.

 