The Most In-Demand Scrum PSK-I Pass Guaranteed Quiz
New Version PSK-I Certificate & Helpful Exam Dumps is Online
NEW QUESTION # 62
True or False: A positive side effect of limiting WIP is that it creates a "pull system".
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 63
The definition of "Workflow" typically includes: (choose the best four answers)
- A. A shared understanding within the Scrum Team of how work is defined (work items).
- B. The active states for the work items.
- C. The start state of the process.
- D. A definition of customer value.
- E. The finished state of the process.
Answer: A,B,C,E
NEW QUESTION # 64
True or False: When using Scrum with Kanban you can release multiple times during the Sprint.
- A. True
- B. False
Answer: A
NEW QUESTION # 65
True or False: Scrum with Kanban only allows you to release at the end of the Sprint.
- A. False
- B. True
Answer: A
NEW QUESTION # 66
The Cumulative Flow Diagram is most helpful in visualizing which of the following two metrics? (choose the best two answer)
- A. Throughput.
- B. Work in Progress (WIP) trends.
- C. Cycle Time trends and distributions.
- D. Where active items are in the workflow and the typical cycle times for the team.
Answer: A,B
NEW QUESTION # 67
What are the benefits of having early, frequent, and consistent feedback loops? (choose the best answer)
- A. Increased customer satisfaction.
- B. Identifying and addressing problems early.
- C. Improved workflows.
- D. All of the above.
Answer: D
NEW QUESTION # 68
What best describes an eight day 85% Service Level Expectation (SLE)? (choose the best answer)
- A. The team expects a work item to be 85% complete by the end of 8 days of when they start the item.
- B. The team expects they will complete a work item within 8 days of starting on it, 85% of the time.
- C. At least 85% of all Product Backlog items finished within 8 days.
- D. 85% of all Product Backlog items are completed with 8 days remaining.
Answer: B
NEW QUESTION # 69
True or False: Cycle time is considered a lagging indicator.
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 70
True or False: Reduced productivity is the result of optimizing WIP limits.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 71
What can happen if the Scrum Team's Work In Progress (WIP) Limit is not honored? (choose the best answer)
- A. Processes will suffer from inefficiency.
- B. Team throughput increases.
- C. Feedback loops become shorter.
- D. Concurrent operations will slow down.
Answer: A
NEW QUESTION # 72
Which of the following are considered Kanban practices for Scrum Teams? (choose the best answer)
- A. T-shirt size estimation, service level expectations, limiting Work in Progress (WIP).
- B. Kaizen, removing bottlenecks, policies radiators, pull system.
- C. Visualizing flow, limiting Work in Progress (WIP), actively manage the Work in Progress (WIP), inspecting & adapting the workflow.
- D. Class of service, measuring cost of delay, visualizing the workflow, limiting Work in Progress (WIP), managing flow.
- E. Small batch sizes, limiting Work in Progress (WIP), eliminating waste, Kaizen.
Answer: C
NEW QUESTION # 73
To effectively track Work in Progress (WIP), a team should clearly define what it means to have 'started' work and to have 'finished' work. This will typically be included in the Scrum Team's definition of "Workflow" policy.
How are these various points of flow defined? (choose the best answer)
- A. However the Developers choose to define it. They have the final say on managing the Sprint Backlog.
- B. Any Product Backlog item in the Sprint Backlog that is not 'done' is considered WIP.
- C. However the Scrum Team decides to define it. The definition must be in agreement with the Developers and the Product Owner.
- D. Product Backlog items that conform with the team's Definition of Ready are considered WIP.
- E. Each point of flow is assigned an owner and will be defined by that owner.
Answer: C
NEW QUESTION # 74
The Scrum Team's Definition of Workflow includes descriptions of each state of a work item can be. True or False: The various states of a work item described in the Definition of Workflow can only encompass flow inside of the Sprint. ie limited to the state of each column on the Developers' Kanban board.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 75
An existing Scrum Team wants to apply Kanban practices.
What can the team start doing get begin achieving flow? (choose the best 4 answers)
- A. Visualizing their workflow.
- B. Ensuring the product backlog is refined frequently.
- C. Actively managing WIP.
- D. Limiting Work in Progress (WIP).
- E. Inspecting & adapting their workflow.
Answer: A,C,D,E
NEW QUESTION # 76
What would be the most appropriate reason for a Scrum Team to adjust their Work in Progress (WIP) Limits? (choose the best answer)
- A. When the work in progress is lower than the capacity of the Developers.
- B. When they want to improve their cycle time, workflow, and focus.
- C. When the velocity of the Scrum Team velocity becomes too low.
- D. When the Developers receive unplanned urgent work during the Sprint.
Answer: B
NEW QUESTION # 77
Which of the following is the core Kanban mechanism to expose process problems and to stimulate collaborative improvement efforts?
- A. A work-in-progress limited pull system.
- B. Cost of Delay.
- C. Monte Carlo.
- D. Flow Efficiency.
- E. Classes of Service.
Answer: A
NEW QUESTION # 78
True or False: The Sprint length can be thought of as the team's batch size with Scrum Teams using Kanban.
- A. TRUE
- B. Choose only ONE best answer.
- C. FALSE
Answer: C
NEW QUESTION # 79
Work Item Age metrics are most helpful in supporting which of the following? (choose the best two answers)
- A. Inspecting and adapting the team's process and definition of Workflow at the Sprint Retrospective.
- B. Being a leading indicator for the length of the feedback loop for a certain Work Item.
- C. Inspecting and adapting the Sprint at the Daily Scrum.
- D. Influencing the team's Service Level Expectation (SLE).
- E. Helping the team estimate the size of Work Items.
Answer: B,C
NEW QUESTION # 80
True or False: The WIP Limit can only be changed during the Sprint Retrospective.
- A. False
- B. True
Answer: A
NEW QUESTION # 81
True or False: In a flow-based system, the number of tasks is not necessarily limited, rather the amount of value-generating work items is limited.
- A. True
- B. False
Answer: A
NEW QUESTION # 82
True or False: The level of collaboration within a Scrum Team will likely reduce when applying Work in Progress (WIP) Limits.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 83
True or False: A team should change their WIP limit, at the Daily Scrum, if an urgent unplanned item enters a Sprint and the team is at the maximum WIP limit.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 84
Which is the LEAST accurate description of Cycle Time? (choose the best answer)
- A. The total amount of time an item is in a state/column.
- B. The length of time a work item takes from idea stage to feedback from users after release to production.
- C. The quantity/number of items that are delivered within a specified period of time.
- D. The length of time from starting work on the item to when it is finished.
Answer: C
NEW QUESTION # 85
Workflow can be thought of as the Scrum Team's policy for which of the following? (choose the best answer)
- A. How to get work done.
- B. What completed work looks like.
- C. How to increase the Team's WIP limit.
- D. Defining when development is complete and validation begins.
Answer: A
NEW QUESTION # 86
True or False: Kanban is a strategy that complements the Scrum framework with a pull system. The Scrum framework by itself also contains elements of a pull system.
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 87
......
PSK-I Free Certification Exam Material with 140 Q&As : https://passtorrent.testvalid.com/PSK-I-valid-exam-test.html